Addendum Addendum Part 1 Part 2
Every now and then are a few minor problems surfaced here and there:
Our Drying was defective. Together with my neighbors, I then opened the dryer and searched for the error. Fortunately, only the capacitor was defective, which provides the necessary starting current. So a new concern for 20 euros and buy a new dryer.
After we had filled the garden with native soil, I have buried two more sprinkler and three water outlets with the associated pipes and electricity cables about 100m in the garden.
For 14.10. we then ordered the turf. Unfortunately I had to put the appointment on the first birthday of my little daughter, as the weather already very changeable and rainy was.
Fortunately, we had perfect weather on the day of laying the turf. Thanks to the support we had moved up to 280m ² 16h grass and rolled. So lawn watering, and a shower. (Thanks Jan)
Then we celebrated with a few friends and family's birthday.
the weekend, I then poured the still stiff foundations for the garage and my neighbors put together the posts for our garden fence.
One Week later we will have the fence elements attached to the post.
with lawn and fence it looks now all quite different.
Friday, November 27, 2009
What Does The Netral Wire Do In A House
Gradually, I have planned for the last 4 months, further work on the house and garden and implemented.
were first additional paving work on the series. We left the house around a paved road and the terrace (4x7m).
Then we wanted the upper soil layer (about 5cm), including removing weeds and distribute the excavation of foundation in the garden. As the excavation (20m ³) was completely mixed with weeds, we have disposed of it and filled the land with approximately 120m ³ of fresh (sieved) soil.
same time, I got the network sockets connected, set the network connection in the house cabinet space under the ceiling, two built-in patch panel and opened all the cables.
After some back and forth, I then aligned with a friend up the satellite dish so that we can finally television. Even with expensive art, it was not so easy to align the dish correctly.
On 5 September, we were then in Völksen (Springer) during lamp factory sales by Paul Mann. Hoping to find maybe one or the other lamp we are on Saturday went there with a friend there. Thank you to my colleague Marc and Stephan for the tip.
It was worth it. For almost everything we bought and planted bulbs on the same day. For the garden I am unfortunately not found it. The table lamp but we are still not appropriate, since the lightweight wall to the kitchen is not finished.
Even before we had a garage or carport considering to build. In mid-August and then we have chosen a (concrete) with attached garage.
Here I had negotiated with several companies. Ultimately have and we decided to tap the company . So
submit planning application and wait .... After 5 weeks we had the approval finally in hand. The building permit for our house had used only 2 weeks!
early November meant to arrive at the garage.
Thursday, November 12, 2009
What Are The Most Affordable Sedans
lot of work and no time to write ....
I the last 3 months I have neglected my site diary, unfortunately, very much. This I will do in the coming days.
Here is a brief summary what all happened: shelves in the house wiring space built
As the weather gets worse and colder now I can do out there any more. So, stay more time to work in the house and nachzupflegen Construction Diary.
Here are 2 pictures ever:
I the last 3 months I have neglected my site diary, unfortunately, very much. This I will do in the coming days.
Here is a brief summary what all happened: shelves in the house wiring space built
- Much of the paving is completed, including a large terrace
- network cabling is ready
- satellite dish is finally adjusted
- lamps all rooms installed (table lamp is missing)
- dryer was broken -> Fixed (starting capacitor replaced)
- mirror cabinet for bathroom, drawers and shoe rack for the entrance area, lounge area for the kitchen purchased and delivered
- glass sliding door between the kitchen and living room in the fall installed (light wall is missing)
- populated land with topsoil
- turf laid
- power cable, irrigation and water outlets buried in the garden / installed
- garden pump put into operation (beyond turf)
- garage ordered, foundations created (delivery Morning!)
- abgeschottert driveway for the delivery of the garage
- garden fence with the neighbor set
- ...
As the weather gets worse and colder now I can do out there any more. So, stay more time to work in the house and nachzupflegen Construction Diary.
Here are 2 pictures ever:
What Ink Do I Use In My Printer For Iron Ons
garage is, and car is in there ....
Today got our garage: 3x9m
early at 8:30 am, the truck stood with lifting device in front of our house. The truck with our garage at that time was still about 50km away and arrived around 9:30. To
11h everything was ready, and at 12:30 I had removed our house wiring compartment and your car in the garage.
UPDATE: Here
are the pictures of setting up our garage:
Here it is in the approach:
with a "crane" with the appropriate lifting device was first growing and then put the actual garage on the foundation.
my well pipe that I drilled in February with the geothermal power runs, now in a tube Duch the foundation directly into the garage. I can thus pump for watering the garden leave in the garage. The power cables and water pipes run through the sprinkler the same hole in the bottom plate of the garage.
A picture of the finished garage I will deliver even more.
Today got our garage: 3x9m
early at 8:30 am, the truck stood with lifting device in front of our house. The truck with our garage at that time was still about 50km away and arrived around 9:30. To
11h everything was ready, and at 12:30 I had removed our house wiring compartment and your car in the garage.
UPDATE: Here
are the pictures of setting up our garage:
Here it is in the approach:
with a "crane" with the appropriate lifting device was first growing and then put the actual garage on the foundation.
my well pipe that I drilled in February with the geothermal power runs, now in a tube Duch the foundation directly into the garage. I can thus pump for watering the garden leave in the garage. The power cables and water pipes run through the sprinkler the same hole in the bottom plate of the garage.
A picture of the finished garage I will deliver even more.